Go to main menu Go to search Go to main content Go to footer

Financial management

Role
Interested in

Can we make changes in the budget during the project's lifetime?

Budget amounts can be reallocated from one cost category to another, and the budget of a cost category can be exceeded (without a maximum limit) if this is fully justified by a project’s needs and the project’s activities remain in line with the application form.

Budget amounts can be re-allocated between partners too. Two types of budget change between partners are possible:

  1. A budget reallocation of up to 20% of the total partner budget stated in the latest approved application form (flexibility rule) A partner’s total budget can be exceeded by a maximum of 20 % of the original total amount if this is compensated by an underspend in the budget(s) of other partner(s). This type of budget reallocation does not require the programme’s formal prior approval but must be reported and justified through the progress report.
  2. A budget reallocation of over 20% of the total partner budget stated in the latest approved application form A budget reallocation between partners greater than the 20% budget flexibility limit requires a formal approval by the managing authority/ joint secretariat and it must be incorporated in the application form through a request for change procedure (“major budget change”). In principle, a major budget change should happen only once during a project’s lifetime.

Budget reallocations between partners and cost categories are possible on the condition that the total amount(s) of Interreg Funds and/or Norwegian funding awarded to a project are not exceeded.

From and until when are the expenses eligible?

Costs for project activities are eligible from the date of the monitoring committee’s approval of the project until the end date of the project.

The end date of the project marks the end of the eligibility period for expenditure, and it is the date by which the last progress report must be submitted to the joint secretariat.

How do I calculate staff costs?

Under Interreg Europe programme rules, staff costs can only be reported according to the fixed percentage method.

It is therefore not possible to use other methods such as the calculation of staff costs on an hourly basis with timesheets.

The staff costs of employees working part-time on the project must be calculated on a real costs basis using a fixed percentage of the gross employment cost (incl. employer’s contributions) in accordance with article 55 (5) of Regulation (EU) No 2021/1060.

Can I report costs for the verification of expenditure of the final progress report?

The project end date marks the end of the eligibility of the expenditure.

This means that by this date:

  • all project activities must be completed (incl. all procedures related to the administrative closure of the project, such as financial control)
  • all payments must have been made, meaning debited from the bank account
  • the last progress report is submitted to the joint secretariat.

Any expenditure incurred, invoiced, or paid after the project end date indicated in the latest approved application form will be ineligible.

Therefore, in order to be eligible, costs for the verification of expenditure of the final progress report have to be paid out before the end date of the project, provided the check itself is be concluded before the end date.

Where can I find country specific information about the verification of expenditure?

Country-specific information, including information about the control system and the verification of expenditure can be found on Interreg Europe website.

Until when are expenditures eligible?

Costs for project activities are eligible from the date of the monitoring committee’s approval of the project until the end date of the project.

The end date of the project marks the end of the eligibility period for expenditure, and it is the date by which the last progress report must be submitted to the joint secretariat.

Can a policy responsible authority receive a budget for a pilot action?

Associated policy authorities do not directly receive funding.

However, their travel and accommodation costs may be paid by the main partner (and reported as external expertise costs).

Where should we include costs for pilot actions in the budget?

Costs for pilot actions should be planned under the different relevant cost categories as for any other project activity.

There is no separate budget to fill in the application form for pilot actions.

As a local authority do we need budget under external expertise to certify our expenses ?

In Interreg Europe, it is responsibility of each Partner State to set up the control system at national level and therefore establish specific rules on how and by whom the project’s expenditure must be certified.

In principle, there are four general options of control systems:

  1. centralised control at Partner State level through a public administrative body
  2. centralised control at Partner State level through a private audit firm
  3. decentralised control through controllers from a central shortlist
  4. decentralised control through an internal or external controller selected by the project partner and approved by the Partner State

In line with article 46 (8) of Regulation (EU) No 2021/1059, in the period 2021-2027 local authorities are no longer allowed to have their own internal controller but they must hire an external controller for the verification of their expenditure.

Therefore, local authorities from countries applying control systems nr. 3 and 4 must indeed plan costs for the certification of their expenses under cost category “external expertise and services”.

However, regional and national authorities from the same countries can have their own internal controller and they are not obliged to plan control costs in "external expertise and services".